Blue Creek Bridge & Mill Creek Road (MP 8.0 to MP 9.4)

CRP-15-01-Before

CRP Number:

15-01 and 10-04

Funding Source:

County and Federal (STPR and FLAP)

Project Cost:

$9.7M

Construction Date:

2018

Completion Date:

2019

The Blue Creek Bridge and the Mill Creek Road projects were combined to save on construction costs. The Blue Creek Bridge project will replace the existing 80 foot bridge with a single span 131 foot bridge. Both roads will be realigned  and widened. The Mill Creek Road will replace an existing 100 ft. bridge with a single span 168 ft. bridge relocating the bridge south to the original channel. Mill Creek Road will also be realigned and widened. Temporary detour bridges will be provided at both sites.

Update:

Blue Creek bridge is combined with the Mill Creek Road project (MP 8.0 to MP 9.4). Due to delays is acquiring right of way for the Mill Creek Road project, construction is expected to begin in the summer of 2018 and continue through 2019.

 

Project Documents:

  • Call for Bids
  • Plans
  • Specifications
  • Addendums
  • Bid Tab
  • Bid Award

Contact Information:
Tony Garcia Morales, PE
Asst. Chief of Engineering and Construction
(509) 524-2710