Touchet Gardena Road


CRP-13-04-Before

CRP Number:
17-02

Funding Source:
County
Project Cost:
$150,000
Construction Date:
July 2017
Completion Date:
August 2017

This project consists of the reconstruction of 588-ft of Touchet Gardena Road MP 0.56 to MP O.99 to improve the transition from road onto Touchet Gardena Bridge, placing extruded curb type 5, planning bituminous pavement, cement concrete pavement grinding, and HMA.

Update:

Project Complete 

Project Documents: (To download Right Click - Save as:)

 

 

Contact Information:
Tony Garcia Morales, PE
Asst. Chief of Engineering and Construction
(509) 524-2710
This email address is being protected from spambots. You need JavaScript enabled to view it.